Planning Concrete Deliveries for a Smooth Pour
Why Planning Matters for Ready-Mix Concrete
Ready-mix concrete is a time-sensitive material. Once the truck leaves the plant, the clock starts ticking. A well-planned delivery ensures the concrete arrives at the right consistency, at the right time, and can be placed before it begins to set. Poor planning, on the other hand, can lead to delays, wasted material, and a compromised slab or foundation. This guide covers the practical steps to take before the first truck rolls up to your site.
Start With the Order Volume
The first step is calculating how much concrete you need. Measure the area of the pour in square metres and multiply by the depth in metres. Add a small allowance for spillage, uneven subgrade, or changes in the ground. A common rule of thumb is to order about 5 to 10 percent more than the calculated volume. This avoids running short on the day. Running out mid-pour is a problem because the next truck may not arrive in time, and a cold joint can weaken the structure.
Discuss the required strength and mix with the supplier. Common grades like C10 for blinding or C30 for foundations each have different setting times and workability. The supplier can advise on the right mix for your project and the expected delivery time from the plant to your site.
Site Access and Vehicle Clearance
Concrete delivery trucks are large and heavy. A standard ready-mix truck is about 8 to 9 metres long, 2.5 metres wide, and can weigh over 30 tonnes when fully loaded. Check the route from the main road to the pouring area. Look for low bridges, narrow gates, sharp turns, steep gradients, and soft ground. If the truck cannot reach the pour site, the concrete will have to be transferred by wheelbarrow or a pump, which adds time and labour.
If the access is tight, consider using a smaller truck or arranging a pump to move the concrete from a nearby access point. Let the supplier know about any restrictions when you order so they can plan the delivery vehicle accordingly.

Preparing the Pouring Area
The ground where the concrete will be placed needs to be ready before the truck arrives. That means the formwork should be complete, the reinforcement in place, and the subgrade compacted and damp. If the ground is too dry, it can draw moisture from the concrete and weaken the surface. If it is too wet, the concrete may not bond properly.
Have enough labour on hand to handle the pour. Concrete must be placed, spread, and compacted within a certain window. If the weather is hot, the concrete will set faster. In cold weather, it will set slower but may need protection from frost. Plan the pour for a time of day when the temperature is moderate and rain is not forecast.
Delivery Time and Traffic Management
Delivery time is not just about the hour of the day. It is about the sequence of trucks. For a large pour, you may need several loads arriving in a steady stream. Coordinate with the supplier to stagger deliveries so that each truck arrives as the previous one finishes discharging. This keeps the concrete fresh and avoids a gap that could cause a cold joint.
If the site is on a busy road or a tight lane, arrange traffic management in advance. Cones, signs, or a banksman can help guide the truck in and out safely. Let neighbours know if the delivery will block a driveway or create noise early in the morning.
Weather and Its Effect on Concrete
Weather is one of the biggest unknowns in concrete work. High temperatures accelerate the setting time, so you may need to add retarder to the mix or schedule the pour for early morning. Rain can wash out the surface if the concrete has not set, leaving a weak, dusty layer. If heavy rain is forecast, it is better to postpone the pour.
Cold weather slows the hydration process. If the temperature is near freezing, the water in the concrete can freeze and expand, cracking the slab. The supplier can advise on cold-weather mixes or accelerators, but protection like insulating blankets may also be needed. Check the forecast for the pour day and the following 24 hours.

Wheelbarrow Access and Pumping
If the truck cannot drive right up to the formwork, you will need a way to move the concrete from the chute to the pour area. Wheelbarrows are a common solution for small jobs, but they require a solid, level path. A muddy or uneven route will slow things down and tire out the crew. For larger pours, a concrete pump is more efficient. The pump truck can sit at the road and send the concrete through a hose to the pour area, even over long distances or up slopes.
Let the supplier know early if you need a pump. Not all suppliers offer pumping, and those that do may need to know the hose length and the height difference between the truck and the pour point.
Communication With the Supplier
A good concrete supplier wants the pour to go smoothly. Provide clear details when you place the order: the mix grade, the volume, the delivery address, and any access constraints. Confirm the delivery time a day before and again on the morning of the pour. If the site is difficult to find, send a what3words location or a photo of the entrance.
Be honest about how long the pour will take. If you think the crew will be slow, say so. The supplier can then adjust the mix to have a longer working time or send a smaller truck so the concrete does not sit in the drum too long.
After the Pour
Once the concrete is in place, the work is not over. The truck driver will need to wash out the drum and chute. Have a designated area for this, away from the fresh concrete and any drainage. The wash water contains cement and fines, which can harm the environment if they enter streams or sewers.
If you are using a pump, the pump operator will need to flush the hose. Plan for that water as well. A barrel or a section of ground that can be cleaned up later works well.

Common Mistakes to Avoid
- Ordering the wrong mix grade for the application, leading to a weak or hard-to-finish surface.
- Underestimating the delivery time and having the truck arrive before the formwork is ready.
- Failing to check the weather and then dealing with rain or freezing temperatures.
- Not having enough labour on site to handle the pour, causing delays and waste.
Putting It All Together
Planning concrete deliveries is mostly about thinking ahead. Measure the volume, check the access, prepare the ground, and talk to the supplier. A little effort before the truck arrives saves time, money, and frustration on the day. For projects in the East Midlands, Stacey Concrete Ltd offers a range of ready-mix grades and can advise on the best approach for your site.